What are Section 278 works? A plain-English guide

Pencil sketch of a plan where the new junction onto the main road, outside the site boundary, is drawn in gold and stamped S278, with the real bellmouth being built behind a row of cones.

If your planning permission says the access has to be built "under a Section 278 agreement" before anyone moves in, and you've nodded along without being entirely sure what that means, this one's for you.

The short version. Section 278 of the Highways Act 1980 lets a highway authority agree with a developer that the developer will pay for, and usually build, changes to the existing public road. A new junction, a right-turn lane, a footway, a crossing, a relocated bus stop, kerbs moved to make a bellmouth. If it's on the road outside your site rather than inside it, it's almost certainly S278 territory.

Why it exists. The road belongs to the authority and they'll be looking after it long after the houses are sold. So they don't let people dig it up on a promise. The agreement sets out what gets built, to what standard, who inspects it, and what happens if the developer walks away halfway through. That last bit is the bond: money held by the authority until the works are finished and signed off.

What's in the box. Drawings of the works, taken through the authority's technical approval. A road safety audit and the designer's response to it. The legal agreement itself, which also covers the authority's checking and inspection fees and any commuted sum towards future maintenance (we've explained those before). Then road space booking, traffic management, construction under the authority's eye, a maintenance period and a final certificate.

Not to be confused with. Section 38, which is for new roads the developer builds and the authority adopts. Most sites of any size need both: the S278 for the junction, the S38 for the estate roads behind it. And Section 184, the simpler route for a domestic dropped kerb.

The one thing in your control. How complete the first submission is. Authorities are busy and every round of comments costs weeks. Good drawings with the boring bits already answered are the difference between a long walk and a very long one.