Section 278 highway works
Accesses, junctions and frontage improvements on the public highway, designed and seen through technical approval, for developers direct or under your own name.
What Section 278 works are
Section 278 of the Highways Act 1980 lets a highway authority enter into an agreement with a developer so that the developer can pay for, and build, works to the existing public highway. In practice that means the things a new development needs on the road outside it: a new access or junction, a right-turn lane, a footway or cycle track, a pedestrian crossing, moving a bus stop, kerb realignment, street lighting, signs and lines.
If a planning condition says the access or junction has to be built before the development is occupied, a Section 278 agreement is usually how it gets done. People shorten it to S278 or just 278 works.
What's involved
Every highway authority runs the process a little differently, but the shape is the same:
- Design. Drawings of the works to the authority's standards: layout, levels, kerbs, surfacing, drainage, lighting, signs and lines, swept paths and visibility splays, with the supporting checks the authority asks for.
- Technical approval. The design goes to the authority's development team, comments come back, the design goes round again. This is where most of the time goes, and where good drawings pay for themselves.
- The agreement. Solicitors on both sides draw up the legal agreement. It covers the bond or cash deposit that protects the authority if the works aren't finished, the authority's fees for checking and inspecting, and any commuted sum towards future maintenance.
- Road safety audit. Most schemes need an independent audit, and a written designer's response to it, before the authority will approve the works.
- Building it. Either the developer's contractor builds the works under the authority's inspection, or the authority builds them and recharges. Road space has to be booked and traffic management agreed.
- Sign-off. Substantial completion, a maintenance period, then final certificate and the bond released.
How we help
We design Section 278 works, take them through technical approval and stay with the job until the road's open. That includes the early feasibility sketch that tells you whether the access will work at all, the full technical submission, answering the authority's comments, organising the road safety audit and writing the response, and liaising with the authority's engineers and your solicitor on the agreement. We've worked on the authority side of the table too, so we know what the checking engineer is looking for.
We work for developers and landowners directly, and as a white-label service for other consultancies and local authority teams who need extra capacity, on your templates and under your name. Either way the job is the same: drawings that get approved without three extra rounds of "just one more thing".
Where we work
UK-wide, with offices in Yorkshire and Wales. Section 278 is national legislation, so the process is the same whether the site is in Hampshire, London, Sussex or Leeds; what changes is the authority's own design guide, and we work to whichever one applies.
Common questions
What's the difference between Section 278 and Section 38? Section 278 is for works to the existing public highway. Section 38 is for new roads that the developer builds and the authority then adopts. Many sites need both: an S278 for the junction onto the main road and an S38 for the estate roads behind it. See our Section 38 page.
Do I need a Section 278 agreement for a dropped kerb? Usually not. Minor works such as a domestic vehicle crossing are normally done under Section 184 instead, which is quicker and simpler. The authority decides which route applies; if in doubt, ask us.
How long does it take? Honestly, longer than anyone wants. Technical approval depends on the authority's workload and how complete the first submission is, and the legal agreement runs alongside. The one thing in your control is the quality of the design that goes in first.
What does it cost? The design fee depends on the size of the works; the authority's fees, the bond and any commuted sums are set by the authority and are separate. We'll give you a clear fee for the design and a plain-English rundown of the other costs to expect before you commit.
Can you work with my existing design team? Yes. A lot of our Section 278 work is for architects, planners and other engineers who need a highways specialist alongside them, quietly and under their own name if that suits.
Read more in our blog: Section 278: a love story and Commuted sums, explained to a normal person.